RUN BOP and riser W/out test: BOP running time from rig up gimbal to rig down gimbal considering 3 sets of auxiliary lines pressure tests (one at surface, one intermediate, one at bottom) not including tripping duration of tubular type riser joints.
POOH riser and BOP: BOP pulling time from rig up gimbal to rig down gimbal not including tripping duration of tubular type riser joints.
First BOP pressure test & LRMP test : First BOP pressure test & LRMP test at mud line after riser connection, as per CONTRACTOR procedure
Additional BOP pressure test & LRMP test : Additional BOP pressure test & LRMP test at mud line during well operations, as per procedure to be proposed by CONTRACTOR (full description required)
各位 谢谢啦